Assessment 1 of 0
Intermediate Project Management: Session Three – Case Study
Time limit: 0
Assessment Summary
0 of 1 Questions completed
Questions:
Information
You have already completed the assessment before. Hence you can not start it again.
Assessment is loading…
You must sign in or sign up to start the assessment.
You must first complete the following:
Results
Assessment complete. Results are being recorded.
Results
0 of 1 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 1
1. Question
Place the tasks in the correct order.
-
This response will be reviewed and graded after submission.
Grading can be reviewed and adjusted.Grading can be reviewed and adjusted.Hint
- Consult architect
- Obtain bank loan
- Obtain building permit
- Clear land
- Excavate
- Pour concrete foundation
- Purchase materials
- Construct frame
- Install doors and windows
- Sheath house
- Roof house
- Install plumbing
- Install heating
- Install insulation
- Install electrical wiring
- Install floors
- Lay-up masonry exterior
- Put up wall board
- Install interior and exterior trim
- Paint walls and trim
- Paint doors and windows
- Backfill foundation
- Grade land
- Landscape
-