Intermediate Project Management: Session Five – Sample Estimation Table
Intermediate Project Management: Session Five – Sample Estimation Table
Assessment Summary
0 of 1 Questions completed
Questions:
Information
You have already completed the assessment before. Hence you can not start it again.
Assessment is loading…
You must sign in or sign up to start the assessment.
You must first complete the following:
Results
Results
0 of 1 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 1
1. Question
Use the formula above and the figures in the table to calculate the estimated time. Place this time in the Te column.
-
Task #
Task Name
To
Tp
Tm
Te
1
Consult architect
2
8
6
2
Obtain bank loan
1
10
5
3
Obtain building permit
5
14
10
4
Clear land
1
4
2
5
Excavate
1
4
2
6
Pour concrete foundation
1
4
2
7
Purchase materials
1
5
3
8
Construct frame
2
6
4
9
Install doors and windows
3
8
6
10
Sheath house
2
5
3
11
Roof house
2
5
3
12
Install plumbing
5
10
7
13
Install heating
1
5
3
14
Install insulation
1
4
2
15
Install electrical wiring
2
6
4
16
Install floors
1
5
3
17
Lay-up masonry exterior
5
20
10
18
Put up wallboard
1
5
3
19
Install interior and exterior trim
3
7
5
20
Paint walls and trim
2
7
5
21
Paint doors and windows
1
4
2
22
Back fill foundation
1
2
1
23
Grade land
1
5
2
24
Landscape
1
5
3
CorrectIncorrect -